Present Today
42
of 46 workers
Absent / Late
3
1 late, 2 absent
Safety Score
96%
this week
Open Issues
2
resolve today
Daily Attendance
| Worker | Role | In | Status |
|---|---|---|---|
| Ramesh Kumar | Mason | 06:42 | Present |
| Suresh Yadav | Mason | 06:48 | Present |
| Kishore Singh | Helper | 06:50 | Present |
| Devi Lal | Bar Bender | 07:02 | Present |
| Mohan Das | Carpenter | — | Absent |
| Rakesh Pal | Electrician | 07:10 | Present |
| Vinod Sahu | Plumber | 07:15 | Present |
| Arvind K. | Painter | 08:00 | Late |
Today's Progress
- Concrete Progress78%Slab L3 — 220m³ poured
- Brick Work62%Block B walls Day 14
- Roof Progress35%Block A truss erection
- Electrical48%Conduit + JB Floor 2
- Plumbing52%DWV + supply L1-L3
- Painting24%Putty primer Block C
Safety & Inspection Checklist
- PPE distribution check ✓
- Scaffold inspection — Block A ✓
- Edge protection L4 ✓
- Fire extinguisher service ✓
- Toolbox talk attendance (32/34)
- First aid kit refill — pending