Meridian Commercial Complex · Story Mode

VK-002 · Commercial Complex · HITEC City, Hyderabad

Brick Work
Stage 5 / 13
Brick Work
08 Dec 2024 · Engineer Kavya Sharma
Customer approved

Story Timeline · 14 stages

Tap any stage

Today at the Site

Live
Weather
31°C · Clear
Workers Present
125
Engineers Present
2
Contractors Working
3 firms
Deliveries Arriving
2 trucks · 14:30
Concrete Pours
1 pour · 48 m³
Inspections
3 scheduled
Safety Status
All clear
Equipment Running
5 / 6
Site Progress Today
+1.2%

Digital Twin

Progress
58
Budget
66
Health
88
Quality
94
Safety
97
CSAT
91
Material Use
78
Labour Util.
88
Equip Use
82

Project Snapshot

Budget₹18.50 Cr
Spent₹12.14 Cr
Workers128
ContractorPrime Builders Ltd
Target Handover2026-09-30
Next Milestone
Roof
Open full dashboard

Live Photo Journey

Planning
Morning10 Aug 2024
Approval
Morning09 Sept 2024
Foundation
Morning09 Oct 2024
Columns
Morning08 Nov 2024
Brick Work
Morning08 Dec 2024
Roof
Morning07 Jan 2025
Electrical
Morning06 Feb 2025
Plumbing
Morning08 Mar 2025